King Road paving is done; mailboxes, trees and bus signs still to come
All lanes and driveways reopened Oct. 20, but the city says crews will keep working along King Road, with lane shifts, flaggers and some side street closures.

King Road is open to normal traffic again, but drivers should still expect some delays as crews finish the last pieces of the road project.
According to the City of Milwaukie's Nov. 3 project update, all travel lanes and driveways reopened the afternoon of Oct. 20. The contractor finished paving Oct. 16 and completed striping and markings by Oct. 19. The city said most of the construction has been finished on time.
What's left
The city said the remaining work includes:
- Installing mailboxes.
- Finishing landscaping on the new planter strips and planting new trees.
- Installing a second RRFB, at Home Avenue. The city said in its Nov. 3 update that this would happen the following week.
- TriMet installing signs at bus stops along the corridor.
The city said drivers may encounter intermittent lane shifts, sections with flaggers and closed side streets while this work continues.
About the project
The project repaves King Road between 43rd and Linwood avenues and adds multi-use paths along the road. The paths connect to the recently built multi-use path on Linwood Avenue. The city lists the budget at $5,185,000, with funding from the Safe Access for Everyone (SAFE) program and the Street Surface Maintenance Program. The project page gives a May 2023 to November 2026 timeline.
The city also asked drivers to follow the 25 mph posted speed. It said keeping everyone on the road safe is a priority for the city and the contractor.
The city held a "Trail or Treat" event on the new paths Oct. 29. It said attendance was significant despite heavy rain.
Questions about the project can go to the city at 503-786-7605 or [email protected].